Check out the latest construction progress at Century City in Makati City, Philippines.
Commonwealth by Century Project Update (May 2016)
Quirino East (Tower 7) is at its 10th floor; excavation works continue for Roxas West (Tower 5) and Quezon South (Tower 8 ) Structural works for Quirino East, Tower 7 of the Century’s first residential development in Quezon City, is on its 10th level advancing 3 floors from last March. Finishing works are ongoing for […]
Milano Residences Project Update (March 2016)
THE MILANO RESIDENCES NEARS COMPLETION Painting works are complete on all floors of the Milano Residences, as well as the setting of tiles for toilets, hallways, and balconies. The landscaping and finishing works on walls and ceiling at the amenity floor are ongoing and scheduled for completion by the end of March 2016. Tile setting […]
Milano Residences Construction Update (3rd Quarter 2015)
The 53-storey Milano Residences is nearing completion Painting works are simultaneously ongoing on all floors of the Italian-inspired Milano Residences while laying of tiles for toilet, hallways and balconies are on the 49th level. Landscaping, masonry works, frame ceiling, and waterproofing have started in the amenity floor, piazza area (ground floor), and the roof deck. […]
The Residences at Commonwealth Construction Update (3rd Quarter 2015)
Quezon South Tower (building 8 ) breaks ground; excavation works begin Commonwealth by Century held the groundbreaking rites for Quezon South tower last August 14, 2015. The ceremony marked the start of excavation works for building 8 of Century’s first residential development in Quezon City. Roxas East tower (building 2), which was topped off last […]
Milano Residences Construction Update (1st Quarter 2015)
The Milano Residences is now on its finishing stages After topping out last year, structural and architectural works in Milano Residences have reached its finishing stages. In general, finishing works for the 53-story residential tower is at its full swing as of the 1st quarter of 2015. Interior and exterior finishing such as partitioning and […]
Centuria Medical Makati Construction Update (4th Quarter 2014)
Centuria Medical Makati completes lower floor clinic spaces and continues finishing works on upper levels Century Properties’ IT-medical outpatient building in Century City, Centuria Medical Makati, is being turned over to unit owners for clinic fit-outs this December. Centuria’s common areas and amenities such as the lobby and roofdeck crown are undergoing final touches and […]
Century City Construction Update (August 2014)
Take a tour through the extraordinary district of branded residences and superlative living – Century City in Makati, Philippines! From the exquisite residential skyscrapers; the elegant and uplifting retail complex; the unique medical outpatient facility; to the exceptional nightclubs situated inside this stunning community, Century City is a one-of-a-kind hotspot for modern Filipinos and global […]
Acqua Construction Update (July-August 2014)
The Niagara and Sutherland towers continue progress towards completion in 2015 Acqua Private Residences’ first two buildings will soon be ready for turnover to residents as finishing activities and interior works continue at The Niagara and Sutherland towers, respectively. While The Niagara is close to completion, the Sutherland tower continues exterior painting works and wall […]
Acqua Construction Update (July 2014)
On the banks of the regenerating Pasig River rise the Acqua Private Residences, a glorious multi-tower development that promises a whole new residential experience. Witness its progress in this latest construction update.