Condominium Towers Construction Update July 2019

Monaco and Bali Towers at Azure North have reached the 27 th and 21 st floors, respectively
Building top off target for Monaco is August while Bali’s structural floors are scheduled for
completion in October.

Project completion dates are September 2020 for Monaco and December 2020 for Bali, including
phase 1 of Azure North amenities Barbados, the third tower, is scheduled for completion in 2022.

The Residences at Azure North is part of a 7 8 hectare mixed use development of Century Limitless
Corporation, a subsidiary of Century Properties Group It is located in North Luzon Expressway
( near Gapan Olongapo Road, Brgy San Jose, City of San Fernando, Pampanga.

Monaco and Bali Towers as of July 9, 2019

Monaco and Bali Towers as of July 9, 2019

Monaco Tower (left) and Bali Tower (right) as of July 9, 2019

Monaco Tower (left)
and Bali Tower (right) as of July 9, 2019

Ground to third floor 90% completed masonry works; ongoing painting and mechanical, engineering, plumbing, and fire protection (MEPF) works

Ground to third floor
90% completed masonry works;
ongoing painting and mechanical, engineering, plumbing,
and fire protection (MEPF) works

4th to 10 th floor ongoing architectural and MEPF works

The Bali Tower from North Luzon Expressway (NLEX)

Ground to third floor 90% completed masonry works; ongoing painting and mechanical, engineering, plumbing, and fire protection (MEPF) works