Asian Century Center Construction Update (1st Quarter 2015)

Asian Century Center construction reaches 7th level

Concrete pouring is on-going at the 7th floor of the Asian Century Center in Fort Bonifacio, on the side of 3rd Avenue.

Meanwhile, concrete pouring activities for the elevator shaft and foundation works of the part of the building located on the side of 4th Avenue are likewise ongoing.

Completion of the structural component on the buildings’ lower area (Basement to the 7th floor, both sides) is targeted for end April.

The Asian Century Center office building, which is a joint development between Asian Carmakers and Century Properties Group, is slated for completion in 2016.

The office tower is located at 27th Street on 3rd & 4th Avenues, Fort Bonifacio, Taguig. The tower is Century Properties’ third project within BGC, following the Essensa East Forbes and South of Market.

 

Facebook
Twitter
LinkedIn

Newsletter Subscription Form

Please complete this form to create an account, receive email updates and much more.
  *
 
 
Please click the icon to request captcha.
*

SCHEDULE A TRIPPING

The minimum schedule date is tomorrow.